Monday, July 4, 2011

Closed Up... Mostly

Long, hot weekend.  Trusses on Friday.  Eves and Door on Saturday.  Roof plywood on Sunday.  Temperatures in the mid-90's.  Generally went through 3-5 T-shirts each day. 


As can be seen in this picture, the roof ply has a gap about 4 feet from the left end.  The truss spacing was off a little bit, so I had to leave the gap, which will be covered by the shingles next week.


I still want to bring in some more mortar on the slab to give it a smoother finish.  Where I did so in the back, the surface is nice.  The rest is really rough, even though the slab turned out better than I'd hoped.

No comments:

Post a Comment